2018 Public Works Improvement Projects


TO VIEW WEEKLY VILLAGE PROJECT UPDATES: Click Here
( If you'd like to receive updates via email, please send your request to:  tmeinholz@waunakee.com )

TO VIEW STH 19/113 ROUNDABOUT UPDATES: Click Here

2018 CROSS STREET IMPROVEMENTS

The Work includes constructing a new two-lane typical street that will connect Cross Street from Water Street to Madison Street. The project will include the following:

  • Remove existing building
  • Construct a storm water bioretention pond on village owned lot north of Cross Street
  • Install new water main on Cross Street
  • Install replacement sanitary sewer on Water Street, Cross Street and N. Madison Street
  • Install new storm sewer on Cross Street
  • Install and grade new street base (gravel)
  • Install new curb and gutter on Cross Street
  • Install new 5-foot wide sidewalk on Cross Street
  • Place a new asphalt street surface
  • Restore any disturbed lawn areas with topsoil and seed
  • Install new street lighting throughout the project

The total cost of the project will be paid for using TID 8 funding in accordance with Village Ordinances and policies.  We do not anticipate any additional cost to property owners for this project.  We anticipate that the contractors will begin the project sometime in spring, pending acquisition of one property.  Once construction begins, the project should be completed in approximately 12-16 weeks, without unforeseen delays, and weather permitting.

Open House Invitation

Open House Presentation

Construction Newsletter

Construction Plans

2018 PUBLIC WORKS IMPROVEMENT PROJECTS

Santa Fe Trail - from North Madison Street to Cheyenne Pass

Topeka Trail – from North Madison Street to Cheyenne Pass

Cheyenne Pass - from Topeka Trail to Lexington Avenue

This summer, the Village of Waunakee will be making street and utility improvements to the roads listed above. These projects will include the following:

  • Remove and replace the existing asphalt street surface
  • Remove and replace the underlying street base materials (gravel)
  • Replace the existing water main and service laterals within Right-of-Way
  • Install storm sewer extensions along portions of Santa Fe Trail and Topeka Trail
  • Replace the existing concrete curb and gutter
  • Replace the existing concrete sidewalk with a 5-foot wide sidewalk
  • Replace the existing driveway aprons with concrete aprons
  • Restore any disturbed lawn areas with topsoil and seed
  • Install new street lighting throughout the project

 The total cost of the project will be paid for using the Village’s general tax levy or utility rates in accordance with Village Ordinances and policies.  We do not anticipate any additional cost to property owners for this project.  We anticipate that the contractors will begin the project sometime in early spring, and the project should be completed in approximately 12-16 weeks, without unforeseen delays, and weather permitting.